| Part and process requirements | Define the resin, part dimensions, projected area, target cycle, annual volume, and quality requirements before comparing presses. | Record the part’s maximum projected area and shot weight, including runners where applicable. Confirm the intended resin and process conditions with the process engineer. | Prepare a part drawing, material specification, expected production volume, and sample or reference part. |
| Clamping force | Check that the press can resist cavity pressure across the total projected area without relying on an unverified tonnage estimate. | A preliminary estimate may use about 2–5 tons of clamp force per square inch of projected area, but the required value depends on resin, part geometry, runner layout, and process conditions. | Ask the mold or process supplier to validate the estimate. Confirm the press has suitable clamp-force adjustment and operating range. |
| Shot capacity and injection unit | Compare the mold’s required shot size and material requirements with the injection unit’s usable capacity. | Check shot capacity in the units used by the supplier, plasticizing capacity, screw diameter, injection pressure, and compatibility with the selected resin. | Request written confirmation that the proposed unit can process the target shot reliably, rather than selecting solely by maximum shot capacity. |
| Mold fit and tie-bar spacing | Verify that the mold fits between the tie bars and within the platens, and that its height and opening requirements are within machine limits. | Compare mold width, height, thickness, maximum opening, daylight, tie-bar spacing, and platen dimensions with the press specifications. | Provide the mold drawing and weight. Confirm mold mounting, locating-ring, ejector, and nozzle-interface requirements. |
| Machine condition: clamp and platens | Inspect platen condition, tie bars, clamp movement, lubrication, guarding, and evidence of leaks, cracks, or unusual wear. | Check movement throughout the opening and closing stroke. Review maintenance history and any repairs to structural or clamp components. | Perform an in-person inspection where possible. Record visible defects and request service records and recent inspection results. |
| Machine condition: injection and hydraulics | Inspect the screw, barrel, nozzle, heaters, hydraulic system or drive system, and controls for wear, instability, or faults. | Run the machine through representative movements and verify that temperatures, pressures, alarms, and cycle functions behave consistently. | Request a documented test run and review alarm history. Have qualified personnel assess electrical and pressure-system safety. |
| Safety and compliance | Check interlocked guards, emergency stops, safety circuits, operating instructions, and applicable local workplace requirements. | Safety requirements vary by jurisdiction and machine configuration; do not assume that a previous installation’s approval transfers to a new site. | Obtain available conformity and safety documentation. Arrange a site-specific safety review before production use. |
| Utilities and facility readiness | Confirm electrical supply, cooling-water capacity, compressed air if required, ventilation, and floor loading. | Use the machine’s actual nameplate and installation documentation for voltage, phase, current, cooling flow, connection sizes, and weight. | Have qualified facility personnel verify utility capacity and connections. Do not size services from a general machine category alone. |
| Delivery and access | Plan the route from the delivery point to the production area, including doors, corridors, overhead clearance, and lifting access. | Confirm shipping dimensions and weight, rigging points, unloading equipment, floor capacity, and the space needed for operation and maintenance access. | Request a delivery and rigging plan. Measure the full route and identify any permits, shutdowns, or special lifting arrangements. |
| Purchase terms and total cost | Compare the complete installed cost, not just the machine purchase price. | Include transport, rigging, installation, electrical and cooling work, tooling changes, spare parts, training, taxes, and commissioning where applicable. | Request an itemized written quotation with machine condition, included accessories, delivery terms, payment schedule, warranty terms, and acceptance criteria. |
| Acceptance testing | Agree in advance how the press will be tested and what constitutes acceptable performance. | Use the intended mold and material where practical. Define checks for safety functions, repeatable operation, process stability, and required production output. | Put test conditions and sign-off responsibilities in writing before purchase or commissioning. |
| Installation schedule | Coordinate delivery, rigging, utility connections, leveling, setup, and commissioning with the production schedule. | Allow time for site preparation and commissioning; the actual schedule depends on machine condition, access, utility work, and supplier availability. | Assign an installation owner and confirm required site readiness, service support, and start-up dates before the press ships. |
| Operator and maintenance training | Plan instruction for safe operation, process setup, routine checks, alarm response, and scheduled maintenance. | Training duration depends on machine controls and staff experience. Include hands-on instruction using the installed press and relevant procedures. | Identify trainees in advance and request training materials, maintenance schedules, troubleshooting guidance, and a record of completion. |
| Spare parts and ongoing support | Confirm access to critical parts, technical documentation, and qualified service after installation. | Prioritize parts based on machine configuration, expected production hours, lead times, and the consequences of downtime. | Request a recommended spare-parts list, parts identification documents, service contact process, and support availability in writing. |