| 1 | Confirm the electrical system | System voltage, frequency, phase, and number of wires, including whether a neutral conductor is required. | Match the switch configuration to the installation—for example, a three-phase system may be 208Y/120 V or 480Y/277 V at 60 Hz. Confirm the actual site supply before specifying equipment. |
| 2 | Size the switch for the load | Continuous load current, expected demand, future expansion, and applicable electrical-code requirements. | Choose a rated current that is suitable for the calculated load and installation. Do not size solely from a generator’s advertised output; have a qualified electrical professional verify conductor, overcurrent-protection, and code requirements. |
| 3 | Check starting and inrush currents | Motor starting current, transformer inrush, and other short-duration load peaks. | Review equipment data for motors, pumps, compressors, and transformers. Confirm that the source and switch can handle starting conditions without nuisance trips or unacceptable voltage drop. |
| 4 | Specify the source arrangement | Which sources will connect to the ATS, such as utility and generator, and which source is preferred during normal operation. | Confirm the number of sources, source voltage and frequency, generator capacity, and the intended normal-source priority. Verify that controls can detect the required source conditions. |
| 5 | Set an acceptable interruption time | The maximum time each load can tolerate without power, including time for the alternate source to become available. | Separate generator start-and-warm-up time from the switch’s operating time. Generator-backed transfer commonly involves a delay of seconds or longer; use a UPS or another ride-through method when loads cannot tolerate that interruption. |
| 6 | Choose the transition method | Whether open, delayed, or closed transition is appropriate for the loads and sources. | Open transition transfers by disconnecting one source before connecting the other. Delayed transition adds a neutral interval. Closed transition briefly overlaps sources and requires suitable synchronization, system design, and any required utility approval. |
| 7 | Review short-circuit and withstand ratings | Available fault current at the installation point and the protection device coordinated with the ATS. | Check the ATS short-circuit current rating and its permitted protective-device combination against the site fault study and upstream protection. A qualified designer should verify coordination. |
| 8 | Decide how the neutral is handled | Whether a solid or switched neutral is required, based on the grounding and source configuration. | Generator grounding and bonding arrangements can affect the required ATS pole configuration. Have the grounding design reviewed rather than assuming that every installation uses the same neutral arrangement. |
| 9 | Check operating environment and enclosure | Indoor or outdoor location, ambient temperature, moisture, dust, corrosion, access, and available wall or floor space. | Select an enclosure with an environmental rating suitable for the installation location. Confirm clearances, cable entry, ventilation, and the manufacturer’s specified operating-temperature range. |
| 10 | Verify controls, testing, and maintenance needs | Transfer-test schedule, alarms, remote monitoring, exercise settings, bypass needs, and service access. | Confirm which voltage and frequency thresholds, time delays, status contacts, and communications are required. Document a safe test procedure and ensure qualified personnel can inspect and service the equipment. |